Sunday, October 26, 2008

Progress of Renovation


AreaDescriptionPlannedStartedCompleted
Whole UnitDismantling of existing fixture26/9/0825/9/0830/9/08
Whole UnitElectrical Point Installation29/9/0827/9/0827/9/08
Living / MBRConstruction of False Ceiling / L-Box2/10/082/10/084/10/08
MBRConstruction of Partition Wall for Wardrobe2/10/082/10/084/10/08
Whole UnitPainting6/10/086/10/088/10/08
Living / MBRInstallation of Lights & Switches8/10/089/10/0810/10/08
MBRInstallation of Walk-in-wardrobe Poles12/10/08TBCTBC
MBRInstallation of Rain Shower12/10/0812/10/0812/10/08
KitchenAlteration of Inlet/Outlet Pips12/10/0812/10/0814/10/08
KitchenConstruction of Kitchen Cabinet Cement Base16/10/0816/10/0817/10/08
Whole UnitAcid Wash13/10/0813/10/0815/10/08
MBRConstruction of Storage Cabinet16/10/0816/10/08TBC
Living / MBRConstruction of Platform16/10/0816/10/08TBC
LivingConstruction of TV Console16/10/0816/10/08TBC
LivingConstruction of Shoes Cabinet20/10/0822/10/08TBC
KitchenConstruction of Kitchen Cabinet20/10/0822/10/08TBC
KitchenInstallation of Sink, Stove & Hood27/10/08TBCTBC
Whole UnitRemoving of Renovation Debris30/10/08TBCTBC
Whole UnitInstallation of Curtain1/11/08TBCTBC
LivingInstallation of LCD TV & Home Theatre17/11/08TBCTBC