| Area | Description | Planned | Started | Completed |
| Whole Unit | Dismantling of existing fixture | 26/9/08 | 25/9/08 | 30/9/08 |
| Whole Unit | Electrical Point Installation | 29/9/08 | 27/9/08 | 27/9/08 |
| Living / MBR | Construction of False Ceiling / L-Box | 2/10/08 | 2/10/08 | 4/10/08 |
| MBR | Construction of Partition Wall for Wardrobe | 2/10/08 | 2/10/08 | 4/10/08 |
| Whole Unit | Painting | 6/10/08 | 6/10/08 | 8/10/08 |
| Living / MBR | Installation of Lights & Switches | 8/10/08 | 9/10/08 | 10/10/08 |
| MBR | Installation of Walk-in-wardrobe Poles | 12/10/08 | TBC | TBC |
| MBR | Installation of Rain Shower | 12/10/08 | 12/10/08 | 12/10/08 |
| Kitchen | Alteration of Inlet/Outlet Pips | 12/10/08 | 12/10/08 | 14/10/08 |
| Kitchen | Construction of Kitchen Cabinet Cement Base | 16/10/08 | 16/10/08 | 17/10/08 |
| Whole Unit | Acid Wash | 13/10/08 | 13/10/08 | 15/10/08 |
| MBR | Construction of Storage Cabinet | 16/10/08 | 16/10/08 | TBC |
| Living / MBR | Construction of Platform | 16/10/08 | 16/10/08 | TBC |
| Living | Construction of TV Console | 16/10/08 | 16/10/08 | TBC |
| Living | Construction of Shoes Cabinet | 20/10/08 | 22/10/08 | TBC |
| Kitchen | Construction of Kitchen Cabinet | 20/10/08 | 22/10/08 | TBC |
| Kitchen | Installation of Sink, Stove & Hood | 27/10/08 | TBC | TBC |
| Whole Unit | Removing of Renovation Debris | 30/10/08 | TBC | TBC |
| Whole Unit |
Installation of Curtain | 1/11/08 | TBC | TBC |
| Living | Installation of LCD TV & Home Theatre | 17/11/08 | TBC | TBC |